GS Breaks Ground on 2.4 GW AI Data Center in Donghae, Asia's Largest-Scale Campus Enters Construction
- Dispatched: Nov 28, 2026 · 02:38 ET (07:38 UTC)
One-sentence summary: South Korea's GS Group broke ground on November 28 on a planned 2.4 GW AI data center campus in Donghae, Gangwon Province, with President Lee Jae Myung in attendance; the first 1.2 GW phase targets completion of its first 100 MW in the first half of 2028, with total investment of up to 120 trillion won (about $82 billion) including GPUs and memory chips.
Verification status: ✓ Official first-hand disclosure (South Korean presidential office statement) cross-confirmed by multiple authoritative outlets (Yonhap, Seoul Economic Daily)
Core Facts & Consensus Delta:
- GS Group (KRX: 078930) held the ceremony on November 28, 2026 (Korea time) at the Bukpyeong No. 2 General Industrial Complex in Donghae; Yonhap first reported it at 2026-11-27 21:55 ET / 2026-11-28 02:55 UTC. About 270 people attended, including President Lee Jae Myung and GS Chairman Huh Tae-soo.
- The campus is planned at 2.4 GW in two 1.2 GW phases. Phase one starts with a 100 MW facility (70 MW of IT load), construction running December 1, 2026 to June 30, 2028, with the full 1.2 GW phase operating by 2029; phase two targets completion in 2030.
- Full 2.4 GW construction is estimated at about 30 trillion won (about $20.5 billion); including GPUs and memory chips, the total could reach 120 trillion won (about $82 billion), with phase one at about 15 trillion won (about $10.2 billion).
- First announced on June 29, 2026, it is the first gigawatt-scale campus to break ground among the three megaprojects the South Korean government announced in June; the Special Act on the Promotion of the AI Data Center Industry takes effect in March 2027.
- GS aims to sign its first customer contract between the end of 2026 and early 2027; no customer name or contract value has been disclosed.
Supply-Chain & Market Read-Through:
- A 2.4 GW campus pulls on compute hardware systematically: GPUs and memory chips account for most of the up-to-120-trillion-won envelope, bearing directly on Nvidia accelerator scheduling and on HBM3E/HBM4 capacity allocation and lead times at the memory makers (SK hynix KRX: 000660, Samsung Electronics KRX: 005930, Micron MU, SanDisk SNDK), whose 2027 HBM supply is already largely sold out — new gigawatt-scale demand tightens allocation negotiations further.
- Regionally, it joins SK Group's AI data center in Ulsan, visited by the president last week, forming an AI compute corridor along South Korea's east coast, with power connection, liquid cooling and optical module supply chains benefiting alongside; the special act taking effect in March 2027 should speed permitting and power approvals.
Next Catalysts & Watchpoints:
- End of 2026 to early 2027: whether GS announces its first customer contract as planned — customer identity, capacity and value are the key verification points.
- March 2027: the Special Act on the Promotion of the AI Data Center Industry takes effect; watch its implementing rules for the approval pace of subsequent gigawatt-scale projects.
- First half of 2028: whether the first 100 MW facility completes on schedule.
Sources:
- Yonhap, via K-VIBE (Published: 2026-11-27 21:55 ET / 2026-11-28 02:55 UTC)
- Seoul Economic Daily (English) (Published: 2026-11-28)
- AI Affairs, citing Yonhap
Information only, not investment advice.
Read full 2026-11-28 daily market brief & cross-asset tape → All flash alerts
More flash alerts from 2026-11-28
- US Regulators Shut United Fidelity Bank in Biggest US Bank Failure Since April 2024✓ VERIFIED
- US Commerce Department Bars Eurasian Backbone Operator RETN From American Networks, Sets January 1, 2027 Exit✓ VERIFIED
- Belgium Orders Google to Halt Data Center Construction After Work Continued Despite Revoked Permit✓ VERIFIED